In the Corporate Finance section of the CFA Level I exam, Capital Budgeting is a core tested topic, and the Payback Period (PB) and Discounted Payback Period (DPB) are high-frequency concepts. Many candidates lose points on calculation details when dealing with these seemingly simple metrics—either forgetting to discount cash flows or making errors in calculator keystroke sequences. This article will guide you from the conceptual fundamentals through hands-on BA II Plus keystrokes, giving you a complete mastery of quick solutions for both types of problems, with supplementary practice using the RBA Calculator (TI BA II Plus iOS app) so you can walk into the exam room with confidence.
Definition: The payback period is the length of time required for the project's undiscounted cumulative cash inflows to exactly cover the initial investment.
Formula:
[
\text{PB} = \text{smallest } T \text{ such that } \sum_{t=1}^{T} CF_t \geq CF_0
]
Where (CF_0) is the initial investment (negative) and (CF_t) is the cash inflow in period t.
Key Characteristics:
- Does not consider the time value of money (i.e., no discounting)
- Measures the "speed of capital recovery," not profitability
- Decision rule: PB < target payback period → accept the project
Definition: The discounted payback period is the length of time required for the project's discounted cumulative cash inflows to exactly cover the initial investment.
Formula:
[
\text{DPB} = \text{smallest } T \text{ such that } \sum_{t=1}^{T} \frac{CF_t}{(1+r)^t} \geq CF_0
]
Where (r) is the project's cost of capital or discount rate.
Key Characteristics:
- Discounts each period's cash flow to its present value (PV) using the cost of capital
- Accounts for the time value of money—more conservative and rigorous than PB
- Decision rule: DPB < target payback period → accept the project
| Metric | Considers Time Value? | Computational Complexity | Use Case |
|---|---|---|---|
| PB | No | Simple | Initial screening of illiquid, high-risk projects |
| DPB | Yes | Moderate | When a more robust payback assessment is needed |
CFA Exam Tip: When calculating DPB, if the discount rate (r = 0), then DPB = PB. This special case frequently appears in conceptual questions—memorize it.
A company is considering a project with an initial investment of $1,000 (CF₀ = -1,000) and expected cash inflows over the next 4 years as follows:
| Year | Cash Inflow (CF) |
|---|---|
| 1 | $500 |
| 2 | $400 |
| 3 | $300 |
| 4 | $200 |
The project's cost of capital (discount rate) is 10%. Calculate:
1. The traditional payback period (PB)
2. The discounted payback period (DPB)
Manual Logic:
- Cumulative Year 1: $500 (still short $500)
- Cumulative Year 2: $500 + $400 = $900 (still short $100)
- Cumulative Year 3: $900 + $300 = $1,200 (exceeds $1,000)
The payback occurs between Year 2 and Year 3. In Year 3, we need to recover the remaining $100, and the full-year cash inflow for Year 3 is $300, so:
[
\text{PB} = 2 + \frac{100}{300} = 2 + 0.33 = \mathbf{2.33 \text{ years}}
]
BA II Plus Keystrokes:
Step 1: Clear the CF register
[2nd] [CLR WORK] → clears all worksheet data
Step 2: Enter cash flows
[CF] enter cash flow worksheet
[2nd] [CLR WORK] clear old data
1000 [+/-] [ENTER] → enter CF₀ = -1,000
[↓] 500 [ENTER] → enter C01 = 500
[↓] [↓] 400 [ENTER] → enter C02 = 400
[↓] [↓] 300 [ENTER] → enter C03 = 300
[↓] [↓] 200 [ENTER] → enter C04 = 200
Step 3: Calculate NPV (for verification) and IRR (optional)
[NPV] → displays I = 0 (we don't need discounting, but set I = 0 first)
10 [ENTER] → enter discount rate 10%
[↓] [CPT] → NPV = 155.16 (for verification; will be used later for DPB)
Note: PB itself doesn't require calculator computation, but the CF worksheet allows you to quickly view cumulative cash flows per period. In practice, PB is usually computed by mental math or a simple cumulative table.
Faster approach (using RBA Calculator):
In the RBA Calculator app, simply enter CF₀ = -1,000, C01 = 500, C02 = 400, C03 = 300, C04 = 200, and the app automatically lists cumulative cash flows—PB is immediately visible.
Manual Logic:
First, discount each period's cash flow to its present value (PV):
| Year | CF | Discount Factor (10%) | PV | Cumulative PV |
|---|---|---|---|---|
| 0 | -1,000 | 1.0000 | -1,000.00 | -1,000.00 |
| 1 | 500 | 0.9091 | 454.55 | -545.45 |
| 2 | 400 | 0.8264 | 330.58 | -214.87 |
| 3 | 300 | 0.7513 | 225.39 | 10.52 |
| 4 | 200 | 0.6830 | 136.60 | 147.12 |
The cumulative PV turns positive in Year 3 (from -214.87 to +10.52). Therefore, DPB occurs between Year 2 and Year 3.
In Year 3, we need to recover the remaining $214.87, and the Year 3 PV is $225.39, so:
[
\text{DPB} = 2 + \frac{214.87}{225.39} = 2 + 0.953 = \mathbf{2.95 \text{ years}}
]
BA II Plus Keystrokes:
Step 1: Enter cash flows (same as PB Steps 1-2)
[CF] [2nd] [CLR WORK]
1000 [+/-] [ENTER]
[↓] 500 [ENTER] [↓] [↓]
400 [ENTER] [↓] [↓]
300 [ENTER] [↓] [↓]
200 [ENTER]
Step 2: Set the discount rate and calculate NPV
[NPV]
10 [ENTER] → enter I = 10%
[↓] [CPT] → NPV = 155.16 (this is the project's total NPV, not DPB)
Step 3: Calculate cumulative discounted cash flows (key technique)
Since the BA II Plus doesn't directly provide DPB, we need to manually accumulate PVs using the CF worksheet. However, the following techniques can help:
Method A: Use the NPV function period by period
- Enter only CF₀ and C01, compute NPV₁ = 454.55 (i.e., Year 1 PV)
- Enter only CF₀, C01, C02, compute NPV₂ = -214.87 (i.e., cumulative 2-year PV)
- Enter only CF₀ through C03, compute NPV₃ = 10.52 (i.e., cumulative 3-year PV)
Method B: Use TVM for intermediate results (shortcut)
In the CF worksheet, after pressing [NPV], the screen displays the NPV value. Pressing [↓] shows other results like NFV (net future value). But the most direct approach is:
[2nd] [QUIT] exit CF worksheet
[2nd] [CLR TVM] clear TVM registers
Then manually compute each period's PV:
[2nd] [CLR TVM]
1 [N] 10 [I/Y] 500 [FV] [CPT] [PV] → -454.55 (take absolute value 454.55)
2 [N] 400 [FV] [CPT] [PV] → -330.58
3 [N] 300 [FV] [CPT] [PV] → -225.39
4 [N] 200 [FV] [CPT] [PV] → -136.60
Manual accumulation: -1000 + 454.55 + 330.58 + 225.39 = 10.52 (cumulative turns positive in Year 3)
DPB = 2 + (1000 - 454.55 - 330.58) / 225.39 = 2 + 214.87/225.39 = 2.95 years
RBA Calculator Recommended: Using the RBA Calculator (TI BA II Plus iOS app), the built-in "Discounted Cash Flow" module allows you to directly input the CF sequence and discount rate, automatically outputting PB, DPB, NPV, IRR, and other metrics—an efficiency tool for pre-exam drilling. Search for "RBA Calculator" in the App Store or visit https://apps.apple.com/cn/app/id1545331477 to download.
Consequence: Residual old data causes errors in NPV and DPB calculations.
Solution: Before starting each new problem, always press [2nd] [CLR WORK] to clear the CF worksheet.
Consequence: Forgetting the negative sign for the initial investment causes cumulative cash flows to always be positive, making PB compute to 0 or a negative value.
Solution: The initial investment is a cash outflow and must be entered as a negative number using [+/-]. For example, enter 1000, press [+/-], then press [ENTER].
Consequence: Mistaking PB for DPB, underestimating project risk.
Solution: DPB requires discounting each period's CF before accumulating. If the problem provides a discount rate, always discount first.
Consequence: Using the wrong numerator or denominator in the fractional portion of PB or DPB.
Solution: The correct formula is:
[
\text{PB} = \text{last year with negative cumulative} + \frac{\text{remaining unrecovered amount}}{\text{next year's cash inflow}}
]
Note that the denominator is next year's cash flow (undiscounted or discounted), not the total cash flow.
Consequence: When the sum of discounted cash flows is less than the initial investment, DPB never recovers—the correct answer is "the project cannot be recovered within its life."
Solution: First calculate the project's total NPV. If NPV is negative, then DPB > project life, and the project should be rejected outright.
A: In the CFA Level I exam, both PB and DPB are commonly tested, but DPB leans more toward calculation (because discounting is required). Recent trends combine them with NPV and IRR in the same question, e.g., "Calculate PB = 2.5 years, DPB = 3.2 years, determine whether the project is acceptable." Be sure to master the calculation logic for both.
A: The BA II Plus has no built-in DPB function; you must manually accumulate discounted cash flows. However, if you use the RBA Calculator (iOS app), its built-in "Discounted Payback Period" function can directly output the DPB result—great for quick verification before the exam. On exam day, use the CF worksheet and TVM functions for manual calculation to ensure accuracy.
A: As the discount rate increases → each period's PV decreases → the cumulative PV takes longer to turn positive → DPB increases. Conversely, as the discount rate decreases → DPB decreases. In the extreme case where the discount rate is 0, DPB = PB. This relationship is frequently tested in conceptual questions.
A: RBA Calculator is an iOS simulator for the TI BA II Plus that supports all financial functions (TVM, CF, NPV, IRR, bonds, etc.) and additionally provides automatic PB/DPB calculation and cash flow chart visualization. For the capital budgeting section, it allows you to drill problems quickly during commutes or spare moments, verify manual calculations, and significantly improve calculation accuracy. Download: https://apps.apple.com/cn/app/id1545331477
| Metric | Formula Core | Decision Rule | Main Limitation |
|---|---|---|---|
| PB | Cumulative undiscounted CF first ≥ 0 | PB < target years | Ignores time value; ignores cash flows after payback |
| DPB | Cumulative discounted CF first ≥ 0 | DPB < target years | Ignores cash flows after payback |
BA II Plus Mnemonic:
- Enter cash flows: CF → 2nd CLR WORK → enter CF₀ (negative sign) → enter C01-Cn period by period
- Calculate NPV: NPV → enter I → CPT
- Manual discounting: 2nd CLR TVM → enter N, I/Y, FV → CPT PV
The payback period and discounted payback period are "entry-level" metrics in capital budgeting, but precisely because they seem simple, candidates often stumble on the details. Master the BA II Plus CF worksheet and TVM functions, practice regularly with the RBA Calculator, and you'll be able to solve PB and DPB problems quickly and accurately on exam day. Remember: PB measures speed, DPB measures quality—combining both gives a comprehensive assessment of a project's liquidity risk. Best of luck to all CFA candidates!