Payback Period (PB) and Discounted Payback (DPB): Concept Overview

The payback period (PB) measures how long it takes for a project's cumulative cash inflows to recover the initial investment. It is the simplest capital budgeting metric and is widely used in practice because it is intuitive and easy to communicate to non-finance stakeholders.

The discounted payback period (DPB) improves on this by discounting all future cash flows at the project's cost of capital before calculating the recovery time. This adjustment captures the time value of money and provides a more economically meaningful measure of risk exposure.

While neither PB nor DPB captures total project profitability, both serve as valuable liquidity and risk screening tools in CFA exam scenarios—especially when management faces uncertainty about long-term cash flows.


When to Use Payback vs. Discounted Payback

Feature Payback (PB) Discounted Payback (DPB)
Time value of money Ignored Incorporated
Cash flows beyond cutoff Ignored Ignored
Risk sensitivity Low Higher
Speed of decision Very fast Moderately fast
CFA Level relevance L1 & L2 L2 & L3

In practice, PB is often used as a quick screen, while DPB serves as a refinement before applying NPV or IRR for the final investment decision.


Worked Example 1: Basic Payback Period

A project requires an initial outlay of $100,000 and generates the following annual cash inflows:

Year Cash Flow
1 $30,000
2 $40,000
3 $35,000
4 $50,000

Step-by-step calculation:

The cumulative cash flow turns positive during Year 3.

PB = 2 + (30,000 / 35,000) = 2.86 years


Worked Example 2: Discounted Payback with BA II Plus

Consider the same project, but with a WACC of 10%. We need to find the DPB.

Step 1: Discount each cash flow

Year Cash Flow PV @ 10%
1 $30,000 $27,272.73
2 $40,000 $33,057.85
3 $35,000 $26,293.65
4 $50,000 $34,150.67

Step 2: Calculate cumulative discounted cash flows

Year Discounted CF Cumulative
1 $27,272.73 $27,272.73
2 $33,057.85 $60,330.58
3 $26,293.65 $86,624.23
4 $34,150.67 $120,774.90

Step 3: Identify the crossover year

After Year 3, cumulative discounted cash flow = $86,624.23. Remaining to recover = $100,000 − $86,624.23 = $13,375.77.

DPB = 3 + (13,375.77 / 34,150.67) = 3.39 years

BA II Plus Keystroke Steps (for discounting verification)

To verify the PV of Year 4 cash flow ($50,000 discounted 4 years at 10%):

1. Press 50000
2. Press [ENTER]
3. Press 4
4. Press [N]
5. Press 10
6. Press [I/Y]
7. Press [CPT] [PV]

Result: −34,150.67 (the negative sign indicates present value received).

Alternatively, if you want to discount all cash flows at once using the CF worksheet:

1. Press [CF] to enter Cash Flow worksheet
2. Enter CF0 = -100000
3. Enter C01 = 30000, F01 = 1
4. Enter C02 = 40000, F02 = 1
5. Enter C03 = 35000, F03 = 1
6. Enter C04 = 50000, F04 = 1
7. Press [2ND] [CLF] to clear any extra rows
8. Press [NPV]
9. Enter I = 10, press [ENTER]
10. Press [↓] to move to NPV
11. Press [CPT] [NPV]

The NPV result confirms the total discounted value, and you can work backward through the cumulative schedule to pinpoint the DPB year.


Worked Example 3: Unequal Cash Flows with DPB

A firm evaluates a project with the following cash flows at a 12% discount rate:

Year Cash Flow
0 −$200,000
1 $60,000
2 $80,000
3 $90,000
4 $110,000

Discounted cash flows:

Cumulative discounted cash flows:

The crossover occurs in Year 4. Remaining after Year 3: $200,000 − $181,198.74 = $18,801.26

DPB = 3 + (18,801.26 / 69,522.66) = 3.27 years


Using RBA Calculator for Faster DPB Calculations

For candidates who study on mobile devices, the RBA Calculator (TI BA II Plus app for iOS) replicates the full functionality of a physical financial calculator, including the Cash Flow worksheet and NPV/IRR computations. This makes it convenient to practice DPB problems during commutes or breaks without needing a physical calculator—simply enter cash flows, set the discount rate, and compute PV values to build the cumulative schedule.


Common Mistakes in Payback Calculations

  1. Forgetting to subtract the initial outlay from cumulative flows. Always start your cumulative table at the initial investment (negative value at Year 0).

  2. Using undiscounted cash flows for DPB. The entire point of DPB is to reflect the time value of money. If you use undiscounted flows, you have simply calculated PB, not DPB.

  3. Rounding too early. Rounding intermediate PV figures can shift the fractional year by 0.01–0.02 years. Carry full precision until the final answer.

  4. Assuming cash flows occur at year-end. The standard convention is end-of-period. If a problem states mid-year convention, you would discount by 0.5, 1.5, 2.5, etc.

  5. Confusing PB threshold with NPV criterion. A short payback does not guarantee positive NPV. Always cross-check with NPV for the final decision.


FAQ: Payback and Discounted Payback

Q1: Can the discounted payback period be shorter than the simple payback?

No. Because discounting reduces the present value of future cash flows, the DPB is always equal to or longer than PB. The only exception is if the discount rate is zero, in which case both are identical.

Q2: Why do CFA exam questions still test PB if it ignores time value?

PB appears frequently in exam questions because it tests your ability to handle cumulative cash flow schedules and fractional-year interpolation. More importantly, the curriculum emphasizes that managers use PB as a screening tool alongside NPV, so understanding its limitations is as critical as computing it.

Q3: What if cash flows are negative in later years?

A negative cash flow in a later year delays payback further. For DPB, it reduces the cumulative discounted balance, potentially extending the recovery period. In extreme cases, the project may never pay back, in which case the DPB is undefined.

Q4: How does DPB compare to NPV as a decision criterion?

DPB tells you when the investment is recovered on a risk-adjusted basis, while NPV tells you how much value the project creates. Neither alone is sufficient—best practice is to use DPB as a risk screen and NPV as the final acceptance criterion.


Key Takeaways

Mastering PB and DPB builds the foundation for understanding more sophisticated metrics like NPV, IRR, and profitability index. Use the RBA Calculator to drill these concepts efficiently on any iOS device.

📱 Need to practice?

RBA Calculator handles all TVM, NPV/IRR and bond calculations, matching the BA II Plus used in exams 100%.