The payback period and discounted payback period are among the most frequently tested capital budgeting concepts in the CFA curriculum. Despite their simplicity, candidates often lose marks due to calculation errors or misunderstanding of the underlying logic. This guide breaks down both metrics, provides a BA II Plus walkthrough, and highlights the pitfalls that trip up test-takers every year.

What Is the Payback Period (PB)?

The payback period measures how long it takes for a project to recover its initial cash outlay from its undiscounted cash inflows. It is expressed in years and answers a straightforward question: "When does the cumulative cash flow turn positive?"

Key Characteristics of PB

Formula

For uniform cash flows:

PB = Initial Investment Ă· Annual Cash Inflow

For non-uniform cash flows, you accumulate year-by-year until the cumulative cash flow equals or exceeds the initial investment, then interpolate the fractional year.

What Is the Discounted Payback Period (DPB)?

The discounted payback period applies the same recovery logic but discounts each future cash flow back to present value using the project's required rate of return (or WACC). This addresses the payback period's most significant flaw—its complete disregard for the time value of money.

Key Characteristics of DPB

Decision Rule

If DPB ≀ the firm's maximum acceptable payback threshold, accept the project. If DPB exceeds the threshold, reject it.

Worked Calculation Example with BA II Plus

Consider Project Alpha with the following characteristics:

Step 1: Calculate Traditional Payback

Cumulative undiscounted cash flows:

Year Cash Flow Cumulative
0 -$100,000 -$100,000
1 $30,000 -$70,000
2 $30,000 -$40,000
3 $30,000 -$10,000
4 $30,000 +$20,000

Payback falls between Year 3 and Year 4:

PB = 3 + ($10,000 Ă· $30,000) = 3.33 years

Step 2: Calculate Discounted Payback

Discount each cash flow at 10%:

Year Cash Flow PV at 10% Cumulative PV
0 -$100,000 -$100,000 -$100,000
1 $30,000 $27,273 -$72,727
2 $30,000 $24,793 -$47,934
3 $30,000 $22,539 -$25,395
4 $30,000 $20,490 -$4,905
5 $30,000 $18,627 +$13,722

DPB falls between Year 4 and Year 5:

DPB = 4 + ($4,905 Ă· $18,627) = 4.26 years

BA II Plus Keystroke Steps for Discounted Cash Flow Calculation

To verify the present values using your BA II Plus:

For each year's discounting:

  1. Press 2nd then FV (to clear TVM registers)
  2. Enter N = 1, I/Y = 10, PV = 0, PMT = 0, FV = -30000
  3. Press CPT then PV → displays $27,272.73

For the full NPV calculation using CF worksheet:

  1. Press 2nd then CLF (clear cash flows)
  2. Enter CF0 = -100000, press ↓
  3. Enter C01 = 30000, press ↓
  4. Enter F01 = 5 (five identical periods), press ↓
  5. Press 2nd then BAL (or CPT → NPV)
  6. Enter I% = 10, press CPT then NPV

The NPV worksheet will confirm the cumulative discounted values align with your manual table.

For candidates studying on their phone or tablet between classes, the RBA Calculator app (the TI BA II Plus iOS app) replicates the full exam-grade calculator experience, including the CF worksheet and all financial functions. Available at https://apps.apple.com/cn/app/id1545331477, it lets you practice the exact keystroke sequences you'll need on exam day.

Common Mistakes Candidates Make

Mistake 1: Forgetting to Interpolate

When the cumulative cash flow turns positive partway through a year, many candidates simply report the full year. Always interpolate the fractional period.

Mistake 2: Using Wrong Discount Rate

Ensure you use the project's hurdle rate or WACC—not the risk-free rate or an arbitrary figure. The discounted payback should use the same rate that NPV uses for internal consistency.

Mistake 3: Confusing Payback with Discounted Payback

In multiple-choice questions, the answer choices often include both PB and DPB values. Read the question stem carefully to confirm which metric is being asked.

Mistake 4: Including Salvage or Terminal Value in the Wrong Year

If a project has a terminal value at the end of its life, it only enters the cumulative calculation at that specific year—not spread across earlier periods.

Mistake 5: Sign Errors in CF Worksheet

On the BA II Plus cash flow worksheet, the initial outlay must be entered as negative. A common error is entering all values as positive, producing an incorrect NPV and misleading payback.

Comparison: Payback vs. Discounted Payback vs. NPV

Feature PB DPB NPV
Time value of money No Yes Yes
Uses all cash flows No No Yes
Decision rule Fixed cutoff Fixed cutoff Positive = accept
Reinvestment assumption N/A N/A Explicit

The CFA curriculum expects you to recognize that payback and discounted payback are supplementary tools—they do not replace NPV. However, they serve practical purposes in risk management and capital rationing scenarios.

FAQ

Q1: Can the discounted payback period be shorter than the regular payback period?

No. Because discounting reduces the present value of future cash flows, the discounted payback will always equal or exceed the traditional payback period. If they are equal, the discount rate is zero.

Q2: How does the CFA exam typically present payback questions?

Most often through a table of cash flows asking you to compute either PB or DPB to two decimal places. Some questions ask you to compare two projects using both metrics and select the superior investment. Be prepared for non-uniform cash flows that require manual cumulative summation.

Q3: Should I memorize the exact BA II Plus keystrokes for payback?

You should be comfortable with the CF worksheet and TVM keys. Payback itself is arithmetic—no built-in function computes it directly. The calculator helps you discount individual cash flows or compute NPV, but the payback interpolation is manual. Practice entering cash flows quickly under time pressure.

Q4: Why does the curriculum still teach payback if it ignores time value of money?

Payback serves as a liquidity and risk proxy. Firms with tight cash constraints or high uncertainty prefer knowing when capital returns. The CFA curriculum acknowledges this practical role while emphasizing that NPV remains the theoretically correct method for value maximization.


Mastering the payback period and discounted payback requires both conceptual clarity and calculator fluency. Practice with varying cash flow patterns—uniform, non-uniform, and those with early negative years—and always verify your discount rate is correct before computing DPB. With focused repetition, these 10-minute concepts become reliable scoring opportunities on the exam.

đŸ“± Need to practice?

RBA Calculator handles all TVM, NPV/IRR and bond calculations, matching the BA II Plus used in exams 100%.

Free Download on App Store

Don't want to download?Try the web calculators →