📅 2026-11-17 📂 Tags: CFA / Net Present Value NPV / NPV 👁 0 views

CFA Exam Core: Net Present Value (NPV) in Practice — Three Worked Examples Explained Step by Step

In the CFA Level I exam, Net Present Value (NPV) is the crown jewel of capital budgeting decisions across the Quantitative Methods and Corporate Issuers modules. Whether you're evaluating a new project, an M&A decision, or asset valuation, understanding the computational logic of NPV and its underlying economic intuition is an essential skill every candidate must master. This article walks you through the concept, three representative worked examples with detailed calculations, and common pitfalls to help you conquer this topic once and for all.

Deep Dive: Net Present Value (NPV) and Capital Budgeting

Net Present Value (NPV) is the sum of the present values of all future cash flows from a project, minus the initial investment cost. Its core logic rests on the Time Value of Money — the principle that $1 today is worth more than $1 in the future.

In capital budgeting decisions, NPV provides the most direct measure of value creation. If NPV is greater than zero, the project generates returns that exceed the required rate of return (typically the risk-free rate plus a risk premium), thereby creating wealth for shareholders. Conversely, if NPV is negative, the project should be rejected.

The basic NPV formula is:

$$NPV = \sum_{t=1}^{n} \frac{CF_t}{(1+r)^t} - CF_0$$

where $CF_t$ represents the cash flow in period $t$, $r$ is the discount rate (typically the Weighted Average Cost of Capital, WACC, or the required rate of return), and $CF_0$ is the initial investment (typically a negative value).

Worked Examples

To help you become proficient with the BA II Plus financial calculator, we've selected three examples covering different scenarios.

Example 1: Basic NPV Calculation

Question:
A company is considering investing in a project with an initial investment ($CF_0$) of 1,000,000. The expected cash flows over the next three years ($CF_1, CF_2, CF_3$) are 300,000, 400,000, and 500,000 respectively. The company's required rate of return ($r$) is 10%. Calculate the NPV of the project.

Solution and BA II Plus Steps:

This problem tests your ability to compute the present value of irregular cash flows. The fastest approach is to use the calculator's Cash Flow Worksheet.

  1. Clear memory: Press 2ND + CE/C (CLR ALL) to ensure the calculator is clean.
  2. Enter Cash Flow Worksheet: Press the CF key.
  3. Enter initial cash flow: The screen displays CF0. Enter -100, then press ↓.
  4. Enter first cash flow: The screen displays C01. Enter 30, then press ↓.
  5. Enter frequency: The screen displays F01. The default is 1. Press ↓.
  6. Enter second cash flow: The screen displays C02. Enter 40, then press ↓.
  7. Enter frequency: The screen displays F02. The default is 1. Press ↓.
  8. Enter third cash flow: The screen displays C03. Enter 50, then press ↓.
  9. Exit worksheet and enter NPV mode: Press the NPV key.
  10. Enter discount rate: The screen displays I. Enter 10, then press ↓.
  11. Calculate NPV: The screen displays NPV. Press the CPT key.

Result: The calculator displays NPV = 3.43.
Conclusion: Since NPV > 0, the project is acceptable.

Example 2: NPV with Terminal Value

Question:
A perpetual project requires an initial investment of 2,000,000. Cash flows for the first three years are 500,000 each. Starting from year 4, cash flows grow perpetually at a rate of 2%, with the year-3 cash flow being 500,000. The discount rate is 8%. Calculate the NPV.

Solution:
The key challenge here is handling the perpetuity growth component. We first calculate the Terminal Value (TV) at the end of year 3, then add it as part of the year-3 cash flow.

  1. Calculate the terminal value: $TV_3 = \frac{CF_4}{r - g} = \frac{50 \times (1+2\%)}{8\% - 2\%} = 866.67$ (in units of 10,000).
  2. The total cash flow in year 3 becomes $50 + 866.67 = 916.67$ (in units of 10,000).
  3. Using the BA II Plus, enter $CF_0=-200$, $C01=50, F01=2$, $C02=916.67$, $I=8$, and compute NPV.

Result: NPV ≈ 2,758,300.

Example 3: Mutually Exclusive Project Selection

Question:
Two mutually exclusive projects, A and B, each require an initial investment of 1,000,000. Project A has an NPV of 100,000, and Project B has an NPV of 150,000. If capital is unlimited, which project should be selected?

Solution:
In mutually exclusive project decisions, even if both projects have positive NPVs, only one can be chosen. The decision rule is to select the project with the highest NPV.

Conclusion: Choose Project B, as it has the higher NPV and creates more value for the company.

Common Mistakes to Avoid

In the actual CFA exam, candidates frequently lose marks on the following details:

  1. Sign errors: The initial investment $CF_0$ must be entered as a negative number, representing a cash outflow. If entered as a positive number, the computed NPV will be artificially inflated, leading to incorrect decisions.
  2. Discount rate confusion: Always use the correct discount rate. For risky projects, use a risk-adjusted rate of return, not the risk-free rate.
  3. Timing misalignment: Confirm whether cash flows occur at the end of each period (Ordinary Annuity) or the beginning (Annuity Due). The BA II Plus defaults to end-of-period mode. If the problem specifies beginning-of-period cash flows, switch to BGN mode (2ND + PMT + BGN).
  4. Omitting terminal value: When using the perpetuity growth model, it's easy to forget to add the terminal value to the final period's cash flow, which underestimates the NPV.

Frequently Asked Questions (FAQ)

Q1: What should you do when NPV and IRR (Internal Rate of Return) give conflicting signals?
A: For independent projects, NPV and IRR typically yield consistent conclusions. However, for mutually exclusive projects with different cash flow patterns (e.g., different scales or timing distributions), the two methods may conflict. In such cases, the NPV rule takes precedence over the IRR rule, because NPV directly measures the increase in shareholder wealth and assumes a reinvestment rate equal to the discount rate, which is more realistic.

Q2: If NPV equals zero, should the project be accepted?
A: Theoretically, NPV = 0 means the project exactly meets the required rate of return, neither increasing nor decreasing shareholder wealth. In practice, considering a risk buffer, managers tend to reject or cautiously evaluate such projects. However, in exam theory, it is treated as a break-even point — accepting or rejecting does not affect total shareholder wealth.

Q3: Does a higher discount rate lead to a higher or lower NPV?
A: A higher discount rate reduces the present value of future cash flows, so NPV will be lower. This reflects the risk-return tradeoff: higher-risk projects typically require a higher discount rate, which lowers their valuation.

Q4: Are there any exceptions to the NPV rule in capital budgeting?
A: Under standard assumptions (independent cash flows, perfect markets), the NPV rule is the gold standard. The only exception arises when a company faces capital rationing, in which case the Profitability Index (PI) should be used to optimize the project portfolio. However, the core logic still serves the goal of maximizing total NPV.

Recommended Exam Preparation Tools

Mastering the financial calculator is critical to passing the CFA exam. Beyond the traditional physical calculator, Apple users can also use RBA Calculator, an iOS app designed specifically for financial computations. It faithfully replicates the functionality of the TI BA II Plus with a user-friendly interface and smooth operation, making it ideal for pre-exam practice and reviewing during spare moments.

👉 Download RBA Calculator (iOS)

By understanding the core logic of Net Present Value, becoming proficient with the BA II Plus, and avoiding common pitfalls in capital budgeting decisions, you'll build strong confidence for the CFA exam. Remember, NPV is more than just a formula — it is the cornerstone of value investing. Good luck with your preparation!

📱 Need to practice?

RBA Calculator handles all TVM, NPV/IRR and bond calculations, matching the BA II Plus used in exams 100%.

Free Download on App Store

Don't want to download?Try the web calculators →